autoUpdateParentTasks
Specifies whether to recalculate the parent task's duration and progress when its child tasks are modified.
The Gantt uses the following rules to determine whether to update a parent task when its subtask is modified.
- A parent task's duration equals a summary duration of its child tasks.
- A parent task and its first child starts at the same time.
- A parent task and its last child ends at the same time.
- A parent task's progress is a summary progress of its child tasks.
enablePredecessorGap
Specifies whether users can move or resize a predecessor to change a gap before a successor according to the dependency rules.
The Gantt component allows users to change the gap between tasks only if they move/resize a successor task. Note that users can use only a successor to create the gap between tasks.
The following image illustrates that the Gantt does not resize the gap between tasks when users move the predecessor:
The enablePredecessorGap option allows users to increase/decrease the gap between the tasks with a predecessor. The Gantt component validates these changes and shifts the successor task to comply with the dependency rules if they are violated.
- <template>
- <DxGantt ... >
- <DxValidation
- :enable-predecessor-gap="true"
- :validate-dependencies="true"
- />
- <!-- ... -->
- </DxGantt>
- </template>
- <script>
- import 'devextreme/dist/css/dx.light.css';
- import 'devexpress-gantt/dist/dx-gantt.css';
- import {
- DxGantt,
- DxValidation,
- // ...
- } from 'devextreme-vue/gantt';
- export default {
- components: {
- DxGantt,
- DxValidation,
- // ...
- }
- };
- </script>
validateDependencies
Enables task dependencies validation.
The Gantt supports the following dependency validation rules:
- Finish to Start (FS) - A successor task's start point should be equal or later than the preceding task's end point.
- Start to Start (SS) - A successor task's start point should be equal or later than the preceding task's start point.
- Finish to Finish (FF) - A successor task's end point should be equal or later than the preceding task's end point.
- Start to Finish (SF) - A successor task's end point should be equal or later than a preceding task's start point.
The Gantt allows you to validate relationships between tasks when they are edited.
User Action | Dependency Type | Gantt's Reaction |
---|---|---|
Move a predecessor task (Task 1) to the left or right. |
Finish to Start (FS):![]() Start to Start (SS): ![]() Start to Finish (SF): ![]() Finish to Finish (FF): ![]() |
The UI component moves a successor task (Task 2) forward or backward to the same time interval. |
Move a successor task (Task 2) to the left. |
Finish to Start (FS):![]() Start to Start (SS): ![]() Start to Finish (SF): ![]() Finish to Finish (FF): ![]() |
This change is denied as it violates dependency rules. The control displays a popup window and suggests the following actions:
|
Move a successor task (Task 2) to the right. |
Finish to Start (FS):![]() Start to Start (SS): ![]() Start to Finish (SF): ![]() Finish to Finish (FF): ![]() |
The control displays a popup window and suggests the following actions:
|