React Gantt - Filter Row

The Gantt component allows users to filter columns by filter row values. To apply filter criteria, users can enter a value in a column's filter row cell or select the value in this cell's editor.

Set the filterRow.visible property to true to display the filter row. Assign false to the columns.allowFiltering property to disable filtering for a column.

DevExtreme HTML5 JavaScript jQuery Knockout Angular Gantt Filtering FilterRow

View Demo

The filter row contains a magnifier icon in its cells. Users can click this icon to select a comparison type from a pop-up list. Set the showOperationChooser property to false for a column to hide the magnifier icon.

DevExtreme HTML5 JavaScript jQuery Knockout Angular Gantt Filtering FilterRow

The Gantt allows you to define initial filter settings in code. Specify a column's filterValue property to apply filter criteria to the column.

jQuery
JavaScript
$(function() {
    $("#gantt").dxGantt({
        columns: [{
            dataField: 'title',
            caption: 'Subject',
            filterValue: 'Scope'
        }, {
            dataField: 'start',
            caption: 'Start Date',
            allowFiltering: false
        }, { 
        // ...
        filterRow: { 
            visible: true
        }
    });
});
Angular
app.component.html
app.component.ts
app.module.ts
<dx-gantt ... >
    <dxo-gantt-filter-row 
        [visible]="true">
    </dxo-gantt-filter-row>
    <dxi-gantt-column
        dataField="title"
        caption="Subject"
        filterValue="Scope">
    </dxi-gantt-column>
    <dxi-gantt-column
        dataField="start"
        caption="Start Date"
        dataType="date"
        [allowFiltering]="false">
    </dxi-gantt-column>
    <!--...-->
</dx-gantt>
import { Component } from '@angular/core';

@Component({
    selector: 'app-root',
    templateUrl: './app.component.html',
    styleUrls: ['./app.component.css']
})

export class AppComponent {
    // ...      
}
import { BrowserModule } from '@angular/platform-browser';
import { NgModule } from '@angular/core';
import { AppComponent } from './app.component';
import { DxGanttModule } from 'devextreme-angular';

@NgModule({
    imports: [
        BrowserModule,
        DxGanttModule
    ],        
    declarations: [AppComponent],
    bootstrap: [AppComponent]
})
export class AppModule { }
Vue
App.vue
<template>
    <DxGantt ... >
        <DxFilterRow 
            :visible="true"
        />
        <DxColumn
            data-field="title"
            caption="Subject"
            filterValue="Scope"
        />
        <DxColumn
            data-field="start"
            caption="Start Date"
            :allowFiltering="false"
        />
        <!--...-->
    </DxGantt>
</template>

<script>
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css'; 

import {
  DxGantt,
  DxFilterRow,
  DxColumn,
  // ...
} from 'devextreme-vue/gantt';

export default {
  components: {
    DxGantt,
    DxFilterRow,
    DxColumn,
    // ...
  }
}
</script>
React
App.js
import React from 'react';
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css'; 

import Gantt, {
    FilterRow,
    Column,
    // ...
} from 'devextreme-react/gantt';

const App = () => {
    return (
        <Gantt ... >
            <FilterRow
                visible={true}
            />
            <Column 
                dataField="title"
                caption="Subject"
                filterValue="Scope"
            />
            <Column
                dataField="start"
                caption="Start Date"
                allowFiltering={false} 
            />
            {/* ... */}
        </Gantt>
    );
};

export default App;
ASP.NET Core Controls
Razor C#
@(Html.DevExtreme().Gantt()
    .Columns(columns => {
        columns.AddFor(m => m.Title)
            .DataField("title")
            .Caption("Subject")
            .FilterValue("Scope");
        columns.AddFor(m => m.Title)
            .DataField("start")
            .Caption("Start Date")
            .AllowFiltering(false);
        @* ... *@
    })
    .FilterRow(e => {
        e.Visible(true);
    })
    // ...
)
ASP.NET MVC Controls
Razor C#
@(Html.DevExtreme().Gantt()
    .Columns(columns => {
        columns.AddFor(m => m.Title)
            .DataField("title")
            .Caption("Subject")
            .FilterValue("Scope");
        columns.AddFor(m => m.Title)
            .DataField("start")
            .Caption("Start Date")
            .AllowFiltering(false);
        @* ... *@
    })
    .FilterRow(e => {
        e.Visible(true);
    })
    // ...
)

The Gantt supports a predefined set of filter operations for each data type.

Underlying dataType defines in-place editor types for filter row cells:

dataType Editor
string, number, object Text box
boolean Drop-down list
date Date picker
datetime Date and time picker

You can use the filterOperations property to specify necessary filter operations for each column.

jQuery
JavaScript
$(function() {
    $("#gantt").dxGantt({
        columns: [{
            dataField: 'title',
            caption: 'Subject',
            filterOperations: ["startswith", "endswith"]
        }, { 
        // ...
        }]
        filterRow: { 
            visible: true,
        }
    });
});
Angular
app.component.html
app.component.ts
app.module.ts
<dx-gantt ... >
    <dxo-gantt-filter-row 
        [visible]="true">
    </dxo-gantt-filter-row>
    <dxi-gantt-column
        dataField="title"
        caption="Subject"
        [filterOperations]="['startswith', 'endswith']">
    </dxi-gantt-column>
    <!--...-->
</dx-gantt>
import { Component } from '@angular/core';

@Component({
    selector: 'app-root',
    templateUrl: './app.component.html',
    styleUrls: ['./app.component.css']
})

export class AppComponent {
    // ...      
}
import { BrowserModule } from '@angular/platform-browser';
import { NgModule } from '@angular/core';
import { AppComponent } from './app.component';
import { DxGanttModule } from 'devextreme-angular';

@NgModule({
    imports: [
        BrowserModule,
        DxGanttModule
    ],        
    declarations: [AppComponent],
    bootstrap: [AppComponent]
})
export class AppModule { }
Vue
App.vue
<template>
    <DxGantt ... >
        <DxFilterRow 
            :visible="true"
        />
        <DxColumn
            data-field="title"
            caption="Subject"
            :filter-operations="['startswith', 'endswith']"
        />
        <!--...-->
    </DxGantt>
</template>

<script>
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css'; 

import {
  DxGantt,
  DxFilterRow,
  DxColumn,
  // ...
} from 'devextreme-vue/gantt';

export default {
  components: {
    DxGantt,
    DxFilterRow,
    DxColumn,
    // ...
  }
}
</script>
React
App.js
import React from 'react';
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css'; 

import Gantt, {
    FilterRow,
    Column,
    // ...
} from 'devextreme-react/gantt';

const App = () => {
    return (
        <Gantt ... >
            <FilterRow
                visible={true}
            />
            <Column 
                dataField="title"
                caption="Subject"
                filterOperations={['startswith', 'endswith']}
            />
            {/* ... */}
        </Gantt>
    );
};

export default App;
ASP.NET Core Controls
Razor C#
@(Html.DevExtreme().Gantt()
    .Columns(columns => {
        columns.AddFor(m => m.Title)
            .DataField("title")
            .Caption("Subject")
            .FilterOperations(new[] { GridFilterOperations.StartsWith, GridFilterOperations.EndsWith });
        @* ... *@
    })
    .FilterRow(e => {
        e.Visible(true);
    })
    // ...
)
ASP.NET MVC Controls
Razor C#
@(Html.DevExtreme().Gantt()
    .Columns(columns => {
        columns.AddFor(m => m.Title)
            .DataField("title")
            .Caption("Subject")
            .FilterOperations(new[] { GridFilterOperations.StartsWith, GridFilterOperations.EndsWith });
        @* ... *@
    })
    .FilterRow(e => {
        e.Visible(true);
    })
    // ...
)