The Gantt component allows users to filter a particular column by values listed in a pop-up window. Users click the filter icon to invoke the window and select the filter criteria for a column.
Set the headerFilter.visible property to true to display filter icons for all columns. Assign false to the allowHeaderFiltering property for a column to disable its filter icon. If this property is not specified, the filtering option depends on the allowFiltering property's value.

You can use a column's filterType property to specify the initial settings of header filter items: all checked (filterType=exclude) or all unchecked (filterType=include).

The header filter contains unique column values. You can change them in the following ways:
Use the groupInterval property to group filter values.
Bind the header filter to a data source.

Users can search for the filter values in the header filter. Enable the headerFilter.allowSearch property at the component level or columns.headerFilter.allowSearch property at the column level to display the search panel. Use the searchMode property to define a comparison type for a specific column.

jQuery
$(function() {
$("#gantt").dxGantt({
columns: [{
dataField: 'title',
caption: 'Subject',
filterType: 'exclude',
headerFilter: {
searchMode: 'startswith'
}
}, {
dataField: 'start',
caption: 'Start Date',
allowHeaderFiltering: false
}, {
dataField: 'end',
caption: 'End Date',
headerFilter: {
groupInterval: 'month'
}
}],
headerFilter: {
visible: true,
allowSearch: true
}
});
});Angular
<dx-gantt ... >
<dxo-gantt-header-filter
[visible]="true"
[allowSearch]="true">
</dxo-gantt-header-filter>
<dxi-gantt-column
dataField="title"
caption="Subject"
filterType = "exclude">
<dxo-gantt-header-filter
searchMode="startswith"
/>
</dxi-gantt-column>
<dxi-gantt-column
dataField="start"
caption="Start Date"
dataType="date"
[allowHeaderFiltering]="false">
</dxi-gantt-column>
<dxi-gantt-column
dataField="end"
caption="End Date"
dataType="date">
<dxo-gantt-header-filter
groupInterval="month"
/>
</dxi-gantt-column>
<!--...-->
</dx-gantt>
import { Component } from '@angular/core';
@Component({
selector: 'app-root',
templateUrl: './app.component.html',
styleUrls: ['./app.component.css']
})
export class AppComponent {
// ...
}
import { BrowserModule } from '@angular/platform-browser';
import { NgModule } from '@angular/core';
import { AppComponent } from './app.component';
import { DxGanttModule } from 'devextreme-angular';
@NgModule({
imports: [
BrowserModule,
DxGanttModule
],
declarations: [AppComponent],
bootstrap: [AppComponent]
})
export class AppModule { }Vue
<template>
<DxGantt ... >
<DxGanttHeaderFilter
:visible="true"
allowSearch="true"
/>
<DxColumn
data-field="title"
caption="Subject"
filterType="exclude">
<DxGanttHeaderFilter
searchMode="startswith"
/>
</DxColumn>
<DxColumn
data-field="start"
caption="Start Date"
:allowHeaderFiltering="false">
</DxColumn>
<DxColumn
data-field="start"
caption="Start Date">
<DxGanttHeaderFilter
groupInterval="month" />
</DxColumn>
<!--...-->
</DxGantt>
</template>
<script>
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css';
import {
DxGantt,
DxGanttHeaderFilter,
DxColumn,
// ...
} from 'devextreme-vue/gantt';
export default {
components: {
DxGantt,
DxGanttHeaderFilter,
DxColumn,
// ...
}
}
</script>React
import React from 'react';
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css';
import Gantt, {
HeaderFilter,
Column,
// ...
} from 'devextreme-react/gantt';
const App = () => {
return (
<Gantt ... >
<HeaderFilter
visible={true}
allowSearch={true}>
<Column
dataField="title"
caption="Subject"
filterType="exclude">
<HeaderFilter
searchMode="startswith">
</HeaderFilter>
</Column>
<Column
dataField="start"
caption="Start Date"
allowHeaderFiltering={false}>
</Column>
<Column
dataField="end"
caption="End Date">
<HeaderFilter
groupInterval="month"
/>
</Column>
{/* ... */}
</Gantt>
);
};
export default App;ASP.NET Core Controls
@(Html.DevExtreme().Gantt()
.Columns(columns => {
columns.AddFor(m => m.Title)
.DataField("title")
.Caption("Subject")
.FilterType(FilterType.Exclude)
.HeaderFilter(headerFilter => headerFilter.SearchMode(CollectionSearchMode.StartsWith));
columns.AddFor(m => m.Title)
.DataField("start")
.Caption("Start Date")
.AllowHeaderFiltering(false)
columns.AddFor(m => m.Title)
.DataField("end")
.Caption("End Date")
.HeaderFilter(headerFilter => headerFilter.GroupInterval(HeaderFilterGroupInterval.Month));
@* ... *@
})
.HeaderFilter(e => {
e.Visible(true)
e.allowSearch(true);
})
// ...
)ASP.NET MVC Controls
@(Html.DevExtreme().Gantt()
.Columns(columns => {
columns.AddFor(m => m.Title)
.DataField("title")
.Caption("Subject")
.FilterType(FilterType.Exclude)
.HeaderFilter(headerFilter => headerFilter.SearchMode(CollectionSearchMode.StartsWith));
columns.AddFor(m => m.Title)
.DataField("start")
.Caption("Start Date")
.AllowHeaderFiltering(false)
columns.AddFor(m => m.Title)
.DataField("end")
.Caption("End Date")
.HeaderFilter(headerFilter => headerFilter.GroupInterval(HeaderFilterGroupInterval.Month));
@* ... *@
})
.HeaderFilter(e => {
e.Visible(true);
e.allowSearch(true);
})
// ...
)The Gantt allows you to define initial filter settings in code. Specify the filterValues property for a column to customize its filter settings.

jQuery
$(function() {
$("#gantt").dxGantt({
columns: [{
dataField: 'title',
caption: 'Subject',
filterValues: ['Deploy software', 'Deployment', 'Deployment complete', 'Testing', 'Unit testing']
}, {
//...
}],
headerFilter: {
visible: true,
}
});
});Angular
<dx-gantt ... >
<dxo-gantt-header-filter
[visible]="true">
</dxo-gantt-header-filter>
<dxi-gantt-column
dataField="title"
caption="Subject"
[filterValues]="['Deploy software', 'Deployment', 'Deployment complete', 'Testing', 'Unit testing']">
</dxi-gantt-column>
<!--...-->
</dx-gantt>
import { Component } from '@angular/core';
@Component({
selector: 'app-root',
templateUrl: './app.component.html',
styleUrls: ['./app.component.css']
})
export class AppComponent {
// ...
}
import { BrowserModule } from '@angular/platform-browser';
import { NgModule } from '@angular/core';
import { AppComponent } from './app.component';
import { DxGanttModule } from 'devextreme-angular';
@NgModule({
imports: [
BrowserModule,
DxGanttModule
],
declarations: [AppComponent],
bootstrap: [AppComponent]
})
export class AppModule { }Vue
<template>
<DxGantt ... >
<DxGanttHeaderFilter
:visible="true"
/>
<DxColumn
data-field="title"
caption="Subject"
:filterValues="['Deploy software', 'Deployment', 'Deployment complete', 'Testing', 'Unit testing']">
</DxColumn>
<!--...-->
</DxGantt>
</template>
<script>
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css';
import {
DxGantt,
DxGanttHeaderFilter,
DxColumn,
// ...
} from 'devextreme-vue/gantt';
export default {
components: {
DxGantt,
DxGanttHeaderFilter,
DxColumn,
// ...
}
}
</script>React
import React from 'react';
import 'devextreme/dist/css/dx.fluent.blue.light.css';
import 'devexpress-gantt/dist/dx-gantt.css';
import Gantt, {
HeaderFilter,
Column,
// ...
} from 'devextreme-react/gantt';
const App = () => {
return (
<Gantt ... >
<HeaderFilter
visible={true}
/>
<Column
dataField="title"
caption="Subject"
filterValues={['Deploy software', 'Deployment', 'Deployment complete', 'Testing', 'Unit testing']}>
</Column>
{/* ... */}
</Gantt>
);
};
export default App;ASP.NET Core Controls
@(Html.DevExtreme().Gantt()
.Columns(columns => {
columns.AddFor(m => m.Title)
.DataField("title")
.Caption("Subject")
.FilterValues(new[] {"Deploy software", "Deployment", "Deployment complete", "Testing", "Unit testing"});
@* ... *@
})
.HeaderFilter(e => {
e.Visible(true);
})
// ...
)ASP.NET MVC Controls
@(Html.DevExtreme().Gantt()
.Columns(columns => {
columns.AddFor(m => m.Title)
.DataField("title")
.Caption("Subject")
.FilterValues(new[] {"Deploy software", "Deployment", "Deployment complete", "Testing", "Unit testing"});
@* ... *@
})
.HeaderFilter(e => {
e.Visible(true);
})
// ...
)